The total target of off-grid power generation capacity was 163.3 megawatts for the year 2014-15. The achievement was 152.86 megawatts for the year 2014-15. It was 93.61% of target of off-grid power generation capacity from new and renewable energy sources in 2014-15.
The target of off-grid power generation capacity from Waste to Power was 10 megawatts for the year 2014-15. The achievement was 21.78 megawatts for the year 2014-15. It was 217.8% of target of off-grid power generation capacity from Waste to Power.
The target of off-grid power generation capacity from Biomass (Non-bagasse Cogeneration) was 80 megawatts for the year 2014-15. The achievement was 60.05 megawatts for the year 2014-15. It was 75.06% of target of off-grid power generation capacity from Biomass (Non-bagasse Cogeneration).
The target of off-grid power generation capacity from Biomass Gasifiers – Rural was 0.8 megawatts for the year 2014-15. The achievement was 0.61 megawatts for the year 2014-15. It was 76.25% of target of off-grid power generation capacity from Biomass Gasifiers – Rural.
The target of off-grid power generation capacity from Biomass Gasifiers – Industrial was 8 megawatts for the year 2014-15. The achievement was 6.15 megawatts for the year 2014-15. It was 76.88% of target of off-grid power generation capacity from Biomass Gasifiers – Industrial.
The target of off-grid power generation capacity from Aero-Generators/ Hybrid Systems was 0.5 megawatts for the year 2014-15. The achievement was 0.27 megawatts for the year 2014-15. It was 54% of target of off-grid power generation capacity from Aero-Generators/ Hybrid Systems.
The target of off-grid power generation capacity from Solar Photo-Voltaic (SPV) Systems was 60 megawatts for the year 2014-15. The achievement was 60 megawatts for the year 2014-15. It was 100% of target of off-grid power generation capacity from SPV Systems.
The target of off-grid power generation capacity from Water Mills (WMs) / Micro/Mini-Hydel Plants was 4 megawatts for the year 2014-15. The achievement was 4 megawatts for the year 2014-15. It was 100% of target of off-grid power generation capacity from Water Mills (WMs) / Micro/Mini-Hydel Plants.
Note: NA: Not Available; Original Source: Ministry of New and Renewable Energy and also published in statistical year book 2016 by MOSPI.
Dataset URL: https://data.gov.in/catalog/programme-wise-cumulative-achievement
Resource Title: 12th Plan Physical Targets and Achievement from 2012-13 to 2014-15